Location is TBD (have a place awaiting confirmation)
Agenda items to include:
Police Report
Update on the Gang of Three by Douglas Development
Update on the 9th and N project by CasRiegler
(Both will be starting demolition this month)
Proposed Alley Closure in Blagden Alley
Covenant for 917 M and hopefully updates on that project along with 1215 9th Street
Below is a narrative update on the Gang of Three thanks to Douglas Development for providing. They will attend on the 18th and be able to answer any questions you might have about the development.
Gang of Three update
27Jun13
Scope of Work
Row houses will be converted into one
property with a shared address – 1218 9th Street NW. Buildings will be a mix of office of
retail. Permitting and construction for
this project are to be broken into two phases:
Phase I: Demolition
and construction of new assemblies required to reach a 1.5 Floor Area Ratio
(FAR). This will include (but not be limited to) permitting and construction of
new exterior and interior walls, a new steel structure with elevated composite
decks and reinforced concrete foundations, electrical service brought to a new
main distribution panel, exterior and interior egress lighting, a fire alarm
system, a new sprinkler system, gas and other dry utilities brought to an
internal distribution point(s), roof drains and storm leaders, functional
restrooms (including a means of exhaust), connection to existing sanitary and
water distribution mains, and a mechanical system that includes the necessities
required for a plant to be sized for future distribution of the completed Phase
II space.
Phase II: Infilling open floor areas (indicated in Phase
I as “Open to Below”) to provide usable and occupiable spaces. This will
primarily be a structural and architectural phase and will also include significant
façade remediation and restoration.
Since this phase on the construction will be on the 9th
Street side of the buildings Douglas Development will have the proper
infrastructure in place to handle and protect pedestrian traffic and limit
street parking in front of the buildings.
Parking & Traffic
Sigal Construction and hired
subcontractors will be using the south parking lot (future Blagden Alley
Residences) as a staging area for construction vehicles. Most of the construction activity for Phase I
will take place on the Blagden Alley side of the rowhouses. We will do our best to limit contractor
parking to the south lot and not block the Alley.
Construction Schedule
We project an 8-month construction
timeline (as of June 2013 – subject to change):
Demolition Permit Issued: July
2013
Start Demo: Mid July 2013
Receive Building Permit /Phase
I Construction: August 2013
Submit for Permit, Phase II:
September 2013
Start Construction, Phase II:
December 2013
Substantial
Completion Phase I & II: February 2014
Construction Team
General
Contractor - Sigal Construction
Architect
– Antunovich Associates
Civil
Engineer – Dewberry Davis
Structural
Engineer – MGV Consulting Structural Engineers
Mechanical,
Electrical, Plumbing Engineer: Hoffman Borowski Associates
Project Contact
Construction (owner): Andrea Gourdine – Project Manager, Douglas
Development Corporation (202-373-2425)
Construction (contractors): Colin Courtillet – Superintendent, Sigal
Construction (ccourtillet@sigal.com)
Leasing opportunities: Michael Leon, Douglas Development Corp
(202-638-6300)
No comments:
Post a Comment